_________________________________________
Staff
Kim
Oatman, P.E., L.S., Director
(270) 809-4387
Pete
Reyna, Senior Project Manager
(270) 809-3990
David
D. Brickeen, Project Manager
(270) 809-4390
Jason
Youngblood, Engineering Technician & CADD Coordinator
(270) 809-6859
Matt
Whittenberg, Engineering Technician
(270) 809-4410
Liz
Anderson, Administrative Secretary
(270) 809-3992
Murray State
University
615 Gilbert Graves
Drive, Murray, KY 42071
(270) 809-3992
(270) 809-3995 Fax
__________________________________________
Purpose
Facilities Design and Construction provides the following services:
- Engineering
- Architecture
- Estimating
- Design Construction Staking
- Construction Management and Administration
- Surveying
- Drafting
The primary task of Facilities
Design and Construction is to assist and support the operations of the
Chief Facilities Officer Associate Vice President for Facilities Management
and all other Facilities Management groups for the implementation of
the following:
- Architectural renovations and additions
- Infrastructure repairs and modifications
- New construction
- Planning, design, cost analysis and feasibility studies for projects
- Construction management and administration on all renovation and
new construction projects
- On some projects, mechanical, electrical and structural engineering
and other consulting services are procured from outside sources. When
services are outsourced Facilities Design and Construction administers
and coordinates these contracts and activities.
Renovations/Reconstruction/Capital
Construction
The Department for Facilities Management has the capability to plan
and carry out all renovation requirements for all University facilities.
There are several different classes of renovation/reconstruction/capital
construction projects. The classes are as follows:
Minor
Renovation/Reconstruction
Less than $500 -- does not require a Renovation Request form. Work will
be accomplished by in-house work order. Over $500 and less than $10,000
with no significant change in building use -- requires Completion of
a Renovation Request form; work will generally be accomplished in-house;
Facilities Management can obtain three bids for outsourced services.
Major
Renovation/Reconstruction
Over $500 and Less than $10,000 with significant change in building
use -- requires Completion of a Renovation Request form; work will generally
be accomplished in-house; Facilities Management can obtain three bids
for outsourced services. Over $10,000 and Less than $50,000--requires
completion of a Renovation Request form; consulting and construction
work will generally be outsourced; Procurement Services administers
construction bidding process.
Capital
Construction Projects
Any new Construction Projects--require completion of a Capital Construction
Project Request form; work will be accomplished in-house and/or outsourced.
Any Renovation/Reconstruction Project Over $50,000--requires completion
of a Capital Construction Project Request form; consulting and construction
work will generally be outsourced; Procurement Services administers
construction bidding process.
* * In some cases, a certain
amount of planning and estimating will be required to determine the
class project. Facilities Design and Construction can help with this.
Projects
of Note:
- New Lee Clark College was completed on schedule for beginning of
Fall 2007 semester.
- Planning has begun for the new Richmond College scheduled to open
in Fall 2009.
- New Public Safety Building is in the bidding phase, planned completion
is Fall 2008.
- Science Complex Clock Tower was substantially completed for Jones
dedication ceremony.
- Biology Second Floor was completed for Fall 2007 semester.
|